Schedule

 Sometime between 2019 and 2021

Mid-Atlantic Power Pathway scheduled to be completed.

 

August 18, 2011

PJM identifies the need for MAPP is now in the 2019-2021 timeframe.

 

October 13, 2010

PJM reaffirmed its previous decision supporting the continued need for MAPP by 2015.

 

August 16, 2010

PJM reaffirms need for MAPP after review.

 

May 5, 2010

PHI proposes Choptank Route for MAPP project.

 

July 2009    

Southern Maryland Critical Area Commission permit received.

 

May 2009       

PJM extends MAPP completion date to 2014 and defers need for Indian River to New Jersey segment to future study.

 

February 2009            

Third round community meetings in Dorchester County, Maryland to receive input on three potential land routes.

 

November 2008          

Second community meetings in Dorchester County, Maryland to receive input on corridors.

 

September 2008          

First community input meetings held in Wicomico County, Maryland.

 

May 2008       

First community input meetings held in Dorchester County, Maryland.

 

November 2007          

First community input meetings held in Prince George's, Charles and Calvert County, Maryland.

 

October 17, 2007        

PJM Interconnection's Board of Managers votes to include MAPP in its regional transmission expansion plan.

 

August 22, 2007

The staff of PJM Interconnection, the independent operator of the Mid-Atlantic power grid, recommends that MAPP be constructed.